Changes & export
Everything that will change in the exported file, and why. Logic, calendars, constraints and baselines are never changed.
Impact summary
The updated programme compared with Plot7_Kingsway_Civils_Programme_Rev06.xml
Mon 25 Jan 2027
Wed 27 Jan 2027
+2 working days
30
later
0
earlier
25
unchanged
112
field changes on 45 rows
New status date Fri 02 Oct
| Activity | Float before | Float now | Used |
|---|---|---|---|
| 37SW drainage Area B - MH21 to MH27now critical | 3d | 0d | 3d |
| 49Kerbing North - Access Road (HB2 & drop kerbs)now critical | 3d | 0d | 3d |
| 52Binder course - Area Bnow critical | 3d | 0d | 3d |
| 53Footpaths, block paving & cycleway - Access Roadnow critical | 3d | 0d | 3d |
| 18Capping layer - Area B | 7d | 4d | 3d |
| 43Utility ducts & draw pits (BT / power) | 4d | 2d | 2d |
| 45Water main & fire hydrants | 4d | 2d | 2d |
| 50Sub-base Type 1 - Area B Access Road | 4d | 2d | 2d |
| Milestone | Uploaded file | Updated | Movement |
|---|---|---|---|
| Foundations handed to steel frame contractor | Wed 07 Oct 2026 | Wed 14 Oct 2026 | +5d |
| Sectional Completion - Area A Service Yard | Mon 19 Oct 2026 | Mon 26 Oct 2026 | +5d |
| Sectional Completion - Area B Access Road | Mon 04 Jan 2027 | Wed 06 Jan 2027 | +2d |
| Contract Completion | Mon 25 Jan 2027 | Wed 27 Jan 2027 | +2d |
Missing information: please confirm
In progress or due by the status date, with no site update this period. Their remaining work has moved to the data date.
- 17Record update
In progress, no update since Fri 25 Sep. Remaining work moved to Mon 05 Oct.
- 25Record update
In progress, no update since Fri 25 Sep. Remaining work moved to Mon 05 Oct.
- 26Record update
In progress, no update since Fri 25 Sep. Remaining work moved to Mon 05 Oct.
- 33Record update
In progress, no update since Fri 25 Sep. Remaining work moved to Mon 05 Oct.
- 34Record update
Due to start Wed 30 Sep, no update received.
- 37Record update
In progress, no update since Fri 25 Sep. Remaining work moved to Mon 05 Oct.
- 38Record update
Due to start Mon 28 Sep, no update received.
- 39Record update
Due to start Tue 29 Sep, no update received.
- 43Record update
Due to start Tue 29 Sep, no update received.
- 44Record update
Due to start Mon 28 Sep, no update received.
- 49Record update
Due to start Thu 01 Oct, no update received.
Change list
Every field that differs from the uploaded file
Progress reported from site, with who reported it.
Nothing has been updated from the site log yet.
Export
Download the updated MS Project XML file
112 field changes across 45 rows.
Import into MS Project via File → Open (XML). Asta Powerproject and P6 can import MS Project XML. Logic, calendars and baselines are unchanged.
Your original file is kept unchanged. Every download is rebuilt from it.