Programme position
Updating to Fri 02 Oct 2026 · data date Mon 05 Oct 2026 · 0 site-log entries
11 activities have no update this period. They were in progress or due by Fri 02 Oct 2026; the remaining work has moved to Mon 05 Oct 2026.
ReviewWed 27 Jan 2027
- Programme start
- Mon 03 Aug 2026
- Data date
- Mon 05 Oct 2026
- Float on completion
- 0 working days
+2 working days
Contract CompletionMon 25 Jan 2027Wed 27 Jan 2027
30
later
0
earlier
25
unchanged
Activity finishes compared with the uploaded file
Completion is later than the uploaded programme. See every change
Overall complete
32.5%
Activities
16of 55 complete
- 16 complete
- 5 in progress
- 34 not started
Late
12
Should have started or finished by Fri 02 Oct 2026 against the baseline
Critical
9
On the critical path, plus 12 near-critical (5 days float or less)
Milestones
Forecast against the baseline, in working days
| Milestone | Baseline | Forecast | Variance | Float | Status |
|---|---|---|---|---|---|
Start on Site | Mon 03 Aug 2026 | Mon 03 Aug 2026 | 0d | — | Achieved |
Access to Area C (Car Park) available from Client | Mon 12 Oct 2026 | Mon 12 Oct 2026 | 0d | 2d | On track |
Foundations handed to steel frame contractor | Wed 07 Oct 2026 | Wed 14 Oct 2026was Wed 07 Oct 2026 (+5d) | +5d | 56d | Late +5d |
Sectional Completion - Area A Service Yard | Fri 16 Oct 2026 | Mon 26 Oct 2026was Mon 19 Oct 2026 (+5d) | +6d | 57d | Late +6d |
Sectional Completion - Area B Access Road | Mon 04 Jan 2027 | Wed 06 Jan 2027was Mon 04 Jan 2027 (+2d) | +2d | 15d | Late +2d |
Contract Completion | Mon 25 Jan 2027 | Wed 27 Jan 2027was Mon 25 Jan 2027 (+2d) | +2d | 0d | Late +2d |
Needs attention
Click an activity for details and quick actions
These were in progress or due by the status date, but nobody has reported on them. Their remaining work has moved to the data date. Please confirm.
Lookahead
Three weeks from the data date, Mon 05 Oct
This week
05 Oct – 11 Oct
Next week
12 Oct – 18 Oct
In 2 weeks
19 Oct – 25 Oct
Progress by WBS
% complete weighted by duration
- Preliminaries & Site Set-up100%
- Earthworks57%
- Piling & Foundations56%
- Drainage - Area A Service Yard85%
- Drainage - Area B Access Road & Area C Car Park14%
- Ducts & Utilities0%
- External Works - Pavements0%
- Landscaping & Handover0%
Progress by Area
From the "Area" custom field
- Area A74%
- Area B12%
- Area C0%
- All44%